Under Part P of the Building Regulations 2010 (Approved Document P, 2013 edition), certain electrical work in dwellings in England has to be notified to Building Control. Paul at All Cabling is a NAPIT registered Competent Person, which means notifiable jobs are self-certified and registered on your behalf — no separate Building Control application, no extra fee to your council.

This page covers England only. Wales, Scotland and Northern Ireland have their own regimes — ask Paul if you're working outside England.

Notifiable work

Must be notified to Building Control — done for you automatically when Paul carries out the work under NAPIT.

  • Installation of a new circuit at any voltage (for example a new radial for an oven, EV charger, shower or outbuilding).
  • Replacement of a consumer unit / fuseboard, or replacement of the main switch.
  • Any addition or alteration to existing circuits in a special location — see the special locations list below.

Non-notifiable work

Still has to comply with BS 7671, but does not need notifying under Part P.

  • Replacing accessories such as socket-outlets, switches and ceiling roses on existing circuits.
  • Replacing a damaged cable on a single circuit on a like-for-like basis.
  • Re-fixing or replacing the enclosure of an existing installed component (provided the circuit's protective measures are unaffected).
  • Providing mechanical protection to existing fixed installations.
  • Additions and alterations to existing circuits outside a special location (e.g. adding a socket or a lighting point in a bedroom or living room).

Special locations

In a special location, any addition or alteration to a circuit is notifiable — not just a new circuit. These are the locations Approved Document P calls out:

  • Rooms containing a bath or shower (Section 701 of BS 7671) — including the zones around the bath/shower.
  • Rooms containing a swimming pool or the surrounds of a swimming pool or paddling pool (Section 702).
  • Rooms with a sauna heater (Section 703).

How Paul notifies your job

  1. 1Design, install and test the work to BS 7671:2018+A4:2026.
  2. 2Issue you an Electrical Installation Certificate (EIC) or Minor Works Certificate with all test results.
  3. 3Notify the work to your local authority Building Control through NAPIT within 30 days.
  4. 4You receive a Building Regulations Compliance Certificate from NAPIT — the document to keep for insurance, remortgage or sale.

Why it matters

  • • Unnotified notifiable work is a breach of the Building Regulations — the local authority can serve an enforcement notice on the homeowner.
  • • Conveyancing solicitors routinely ask for Part P certificates on any recent electrical work when you sell.
  • • Insurers may decline claims arising from unnotified or uncertified electrical work.
  • • Retrospective regularisation through Building Control is possible but slower and more expensive than doing it right the first time.